var requestedWidth = 0;
if(requestedWidth < 400){ requestedWidth = 400; }
The gap between the two sides of the Mississippi River where the I-35W bridge is being constructed. (Pioneer Press: Richard Marshall)
if(requestedWidth > 0){ document.getElementById(‘articleViewerGroup’).style.width = requestedWidth + “px”; document.getElementById(‘articleViewerGroup’).style.margin = “0px 0px 10px 10px”; }

On the 338th day, will the breach finally be closed?

Builders of the new Interstate 35W bridge have circled Independence Day on their calendars for an important milestone in the $234 million project — completion of the main span over the Mississippi River, and the first day the bridge will cross the river since Aug. 1.

“That is what we’re shooting for,” said Amy Barrett, a spokeswoman for Flatiron-Manson, the joint venture building the bridge.

While Barrett and the Minnesota Department of Transportation caution that much would need to go right to hit that target date, Project Manager Peter Sanderson told a group of spectators over the weekend that he hoped to lower the last of 120 concrete bridge segments into place July 4.

If so, Interstate 35W would cross the river barely 11 months after it collapsed during rush hour, killing 13 and injuring 145. The National Transportation Safety Board continues to investigate the cause.

MnDOT spokesman Kevin Gutknecht said no special ceremony is planned to mark the occasion.

“At this point, no,” Gutknecht said. “Our focus is on building this thing well and building it safely.”

Barrett also said there is no significance to the July 4 date. It’s merely a coincidence the span would be completed on Independence Day.

Workers are in the process of lifting 120 U-shaped, 200-ton concrete segments into place. The segments will form the main span over the river and must be handled with care, meaning workers


Advertisement
GetAd(’tile’,'box’,'/home_article’,”,’www.twincities.com’,”,’null’,'null’); on error resume next ShockMode = (Isobject(Createobject(“ShockwaveFlash.ShockwaveFlash.7″)))

can place only four a day.

Barrett and Gutknecht said weather and other factors could affect the completion date, cautioning that mid-July is a safer bet. Over the weekend, for example, high winds delayed the placement of two segments.

Completion of the main span does not mean the bridge is on the cusp of opening. Much work remains on the approach spans and other areas. Flatiron-Manson’s contract with MnDOT only requires the bridge be completed by Christmas Eve.

But with round-the-clock crews, the project is far ahead of schedule and within striking distance of a Sept. 15 completion date that would earn Flatiron-Manson a $20 million bonus. The pace even may mean the possibility of completion by the Sept. 1 opening of the Republican National Convention, though no one connected with the project has stated that as a goal.

So far, about 20 of the 120 concrete segments have been placed. Each was formed on an abandoned stretch of I-35W south of the collapse site and trucked to a riverside park.

There, segments are placed on a barge, floated upriver and carefully lifted into place by a 650-ton-capacity crane. Then, each segment is tied into place using highly tensioned steel. A final 6-foot gap between the bridge’s two sides will be filled with concrete.

Jason Hoppin can be reached at 651-292-1892.