July 8, 2008
-
I-35W Bridge over the MississippiJuly 7, 2008
Greetings! If you have questions, please do not reply directly to this email. Contact
Amy Barrett, Public Information Officer, at (612) 236-6901 or via e-mail at abarrett@flatironcorp.com.Main Span Nears Completion
The day after Minneapolis celebrated the Fourth of July with fireworks over the Mississippi (above), construction crews installed the last of the 60 pre-cast segments for the northbound span of the bridge (below). Crews will install the final 14 segments for the southbound span this week.
Crews will fill the gaps between the cantilevers with two “closure pours” of cast-in-place concrete–one this week for the northbound span and the other next week for the southbound span.Construction Update
Other construction activities scheduled for the week of July 7 include:
- Pouring the concrete for Span 4 (in the areas where the green epoxy-coated rebar has been placed, above), which connects Pier 4 to Abutment 5 on the north side of the river.
- Removing the falsework (temporary support structures) under the approach span on the south side of the river.
- Additional highway paving between University Avenue and Fourth Street Southeast, including the medians, shoulders and ramps.
- Installing light poles along the highway south of Washington Avenue and the northbound entrance ramp from Washington Avenue to I-35W (several light poles were installed last week along the highway on the north side).
- Grading and other roadwork in preparation for paving the highway from Washington Avenue to the abutment wall on the south end of the bridge.
Potential Noise Impacts
- As crews pave the roadway on the north side of the project, backup alarms may be increasingly noticeable in that area, especially at night.
- Following paving, crews will cut expansion joints in the concrete once it has cured. This work involves saws that will create noise intermittently during the day and night.
- Toward the end of the week, crews will need to remove sheet pile near the new retaining wall along the exit ramp from northbound I-35W to University Avenue. This work will take approximately two days to complete and will require the use of equipment that causes noise and vibrations. Because this work can be loud, it will only be done during the day, between 7 a.m. and 9 p.m.
Potential Traffic Impacts
As the project progresses, residents and commuters may encounter activities that will affect traffic in the area. In particular:
- The right lane of University Avenue will be closed from 7 p.m. Thursday to 6 a.m. Friday while the entrance and exit ramps are paved with concrete.
- During roadway paving operations, concrete trucks will travel from the concrete plant on I-35W south of Washington Avenue through the project site and up the northbound ramp to Washington Avenue. Trucks will go left on Washington Avenue to 19th Avenue, then across the 10th Avenue bridge to the north side of the project. Most of this activity will take place at night. There will be traffic control at the top of the ramp at Washington Avenue.
- Construction traffic will continue in the vicinity of the site. Some of the streets affected include Second Street Southeast (between 11th Avenue Southeast and Sixth Avenue Southeast), First Street South, Second Street South (between 13th Avenue South and 11th Avenue South), 19th Avenue South and Bluff Street.
- Due to large crowds attending Sidewalk Superintendent Talks, the bike lane on the west side of the 10th Avenue Bridge will be closed from 11 a.m. until noon on Saturdays until further notice in an effort to ensure the safety of everyone using the bridge. Signs are posted at each end of the bridge noting the restriction. Bikes and pedestrians should use the east side of the bridge between 11 a.m. and noon on Saturdays.
Potential Light Impacts
Crews are working night shifts seven days a week on both sides of the river. Lights and construction traffic may be noticeable around the clock.
Planning Your Route to Downtown Minneapolis – If you are planning to drive to downtown Minneapolis, you can use the links below to plan your route:Getting a Closer Look
Tune in to KSTP-TV - Mn/DOT Project Manager Jon Chiglo will discuss the final steps of connecting the main spans of the bridge during a live interview with KSTP-TV, Channel 5 at 6:10 a.m. Monday, July 14.Attend a Sidewalk Superintendent Talk - These weekly events provide an opportunity to accompany project representatives on a walk across the 10th Avenue Bridge, where you can see the construction workers in action and ask questions about the project. If you’d like to participate, meet in the parking lot in front of the former Grandma’s restaurant at 19th and Washington avenues by 11 a.m. on any Saturday.Take a self-guided tour - Signs describing the design/build process are mounted along the 10th Avenue Bridge.Call the hotline - If you have any questions about the project, please call the hotline at (612) 236-6901 between 7 a.m. and 8 p.m. daily. Messages left after 8 p.m. will be returned first thing the morning of the next business day.Request a presentation - Representatives of Mn/DOT and Flatiron-Manson are willing and eager to provide project updates to neighborhood associations, business associations and other groups. To arrange a presentation, please call the hotline, (612) 236-6901.Other than viewing what’s happening from the 10th Avenue Bridge, the public is asked to stay away from the bridge construction area for safety reasons.The Minnesota Department of Transportation (Mn/DOT) and the Flatiron-Manson construction team intend to build a high quality and safe bridge while minimizing disruptions to the surrounding neighborhoods.We will continue to distribute updates weekly and welcome your comments on how to improve the communication process between the project team and the community.For more information on the I-35W project visit www.mndot.govor call the I-35W Bridge Hotline at (612) 236-6901.