March 1, 2008
-
I-35W Bridge over the MississippiFeb. 29, 2008
Greetings! If you have questions, please do not reply directly to this email. Contact Amy Barrett, Public Information Officer, at (612) 236-6901 or via e-mail at abarrett@flatironcorp.com.
Bridge work will create noise on the north side next week
The next phase of construction at the I-35W Bridge site will involve installing some steel supports (H-piles) on the north side, which will generate noise and vibrations in the immediate vicinity for about three days next week. Crews need to install H-piles for the excavation of one of the 40-foot retaining walls that will stand beside the freeway entrance and exit ramps at University Avenue. The installation procedure will involve drilling or vibrating, which is different from — and much less disruptive than — the pile driving that was done at Abutment 1 in November.
Starting next week, crews will also be operating a concrete crusher, which will break up the pieces of the old roadway so that they can be recycled and used for the base of the rebuilt I-35W roadway. While the crusher is in use, additional noise — including a loud, steady hum and back-up alarms — will be noticeable. This work will take approximately a week to complete.
Both pile installation and concrete crushing will only occur between 7 a.m. and 6 p.m. Monday through Saturday.
Construction Update
Crews removed the steel forms from Pier 3 southbound over the weekend, revealing the first look at the arched concrete columns inside (see photo above). Since it was too cold to leave the columns exposed to the harsh winter air, crews immediately wrapped them in insulating blankets. When the concrete cures more completely and the weather warms up, the blankets can be removed.
Another Milestone — Last Footing Complete
The footing at Pier 3 northbound was completed this week, which was the last footing for the main bridge. This is a significant milestone because the main bridge is now officially “out of the ground.”
Other progress this week:
- pouring the top sections (or “lifts”) of two columns at Pier 4 southbound; and
- pouring three pre-cast segments in the casting yard, bringing the total number of completed segments to seven of the 120 needed for the main span.
Additional progress – for the record:
- approximately one-third of the 48,700 cubic yards of concrete needed for the bridge has been poured (the photo above shows an operator in the control room at the Cemstone plant in Minneapolis, one of the two local Cemstone plants supplying all of the concrete for the bridge);
- approximately 400 of the projected 650 workers needed to build the bridge are now on the job;
- workers logged more than 41,000 man hours on the project in February, up from 22,065 hours in January.
Work scheduled the week of March 3 includes:
- pouring the top lift of the columns at Pier 2 southbound;
- placing rebar in the forms for the side spans on the south side;
- building the supports for the side spans on the north side;
- pouring the first two lifts of the columns at Pier 3 northbound; and
- pouring the top lift of one of the columns at Pier 4 southbound.
Night shifts to begin in casting yard
Crews will pour an average of one segment a day in the casting yard next week. To accomplish this, night shifts will begin on Monday, March 3. Although most of the work will occur inside the enclosed heating shelters, people living and working nearby may notice some lights and noise between 6 p.m. and 4:30 a.m.
Getting a Closer Look
Try the touch-screen kiosks at Mill City Museum and the airport –
Touch-screen kiosks that provide a variety of information about the bridge, including a photo gallery, a timetable and animations showing what the finished bridge will look like from a helicopter, a boat and a car are available in the Mill City Museum lobby and at Concourse C at the Minneapolis-St. Paul International Airport.Visit the website – If you haven’t been to the website for a while, you should take a look. It includes information about Smart Bridge technology and cold weather construction and includes a Virtual Sidewalk Tour with graphics and information on the construction process as well as animations showing the finished bridge from the vantage point of a helicopter, a boat and a car.
Access the webcams – Two webcams are now in place to show what is happening at the construction site. One provides a panoramic view of the entire site, looking east from a rooftop on the north side of the Mississippi River. The other camera is mounted on a light pole on the 10th Avenue Bridge and will provide periodic close-ups on construction activities. To see the webcam views, visit the project website at www.mndot.gov.Attend a Sidewalk Superintendent Talk - These weekly events provide an opportunity to accompany project representatives on a walk across the 10th Avenue Bridge, where you can see the construction workers in action and ask questions about the project. If you’d like to participate, meet in the parking lot in front of Grandma’s restaurant at 19th and Washington Avenues by 11 a.m. on any Saturday.Take a self-guided tour - Signs describing the design/build process are mounted along the 10th Avenue Bridge.Call the hotline - If you have any questions about the project, please call the hotline at 612-236-6901 between 7 a.m. and 8 p.m. daily. Messages left after 8 p.m. will be returned first thing the next morning.Request a presentation - Representatives of Mn/DOT and Flatiron-Manson are willing and eager to provide project updates to neighborhood associations, business associations, and other groups. To arrange a presentation, please call the hotline, 612-236-6901.Other than viewing what’s happening from the 10th Avenue Bridge, the public is asked to stay away from the bridge construction area for safety reasons.The Minnesota Department of Transportation (Mn/DOT) and the Flatiron-Manson construction team intend to build a high quality and safe bridge while minimizing disruptions to the surrounding neighborhoods.We will continue to distribute updates weekly and welcome your comments on how to improve the communication process between the project team and the community.For more information on the I-35W project visit www.mndot.govor call the I-35W Bridge Hotline at 612-236-6901.