  • http://kstp.com/article/stories/s211922.shtml?cat=1

    Breakdown of bridge replacement costs

    The Minnesota Department of Transportation said Monday that costs stemming from the Interstate 35W bridge collapse could approach $400 million.

    The federal government has pledged $250 million. Here is a breakdown of the cost estimate:

    -$234 million for the apparent winning reconstruction bid

    -$27 million in possible incentives for early completion

    -$59 million for right-of-way, utility and environmental mitigation agreements

    -$20 million to reconfigure roads used in traffic reroutes

    -$18 million for demolition and debris removal

    -$18 million in added operational costs at MnDOT, including added inspections

    -$17 million in other government response costs

    Source: Minnesota Department of Transportation

    (Copyright 2007 by The Associated Press. All Rights Reserved.)

    AP-NY-10-01-07 1432EDT