Breakdown of bridge replacement costs
The Minnesota Department of Transportation said Monday that costs stemming from the Interstate 35W bridge collapse could approach $400 million.
The federal government has pledged $250 million. Here is a breakdown of the cost estimate:
-$234 million for the apparent winning reconstruction bid
-$27 million in possible incentives for early completion
-$59 million for right-of-way, utility and environmental mitigation agreements
-$20 million to reconfigure roads used in traffic reroutes
-$18 million for demolition and debris removal
-$18 million in added operational costs at MnDOT, including added inspections
-$17 million in other government response costs
—
Source: Minnesota Department of Transportation